Referendum Building Projects Update
Updates on the NCSD Building Referendum Planning Process
update on north crawford building referendum projects
The North Crawford School District has finalized the selection of projects to be completed within Phase 1 and Phase 2 of our $4.5 million facility referendum. These projects will bring our building and grounds up to date, and address any state and federal regulations that the district was not meeting.
PHASE 1 PROJECTS
School Building Reroof
The school building still has the original 1992 and 1996 ballasted roof. The old ballast and membrane will be removed. Insulation will be replaced as needed, an underlayment will be installed, and a new semi-adhered membrane will be installed. The new roof should save the district thousands of dollars a year in maintenance and energy costs.
Current Ballasted Roof
Visible Signs of a Leaky Roof
Example of Adhered White Rubber Membrane Roof
Exterior Upper EIFC Replacement
The district will be removing the upper exterior stucco walls, and replacing those with a horizontal steel siding in a complimentary color to the existing brick. Replacement of the EIFC will prevent further leakage into the building, as well as give the building a more modern look and design.
View of current upper exterior EIFC
Example of Horizontal Steel Siding
Example of Horizontal Steel Siding
exterior window replacement
The district will replace all exterior ground floor and second floor windows with new, energy efficient, horizontal slide windows.
Ground Floor Window
Upper Windows
Example of Horizontal Slide Window
bathroom/shower addition & renovation
The district will add four brand new family style bathrooms. Additionally, the district will renovate all shower rooms in the building. One new bathroom will be located behind the large gym, with three bathrooms located off the cafeteria and performance center. Both projects will bring the district up to code and will meet all Americans With Disabilities Act (ADA) compliance.
Current Shower Room
Location of New Restrooms
Example of Single Stall Showers
resurfacing of north, west, and south parking lots
The district will be tearing out the old asphalt parking lots, and replacing the north (staff), west (student), and south (staff) asphalt lots with new concrete parking lots.
Current Asphalt Parking Lot
Current Asphalt Parking Lot
Example of Concrete School Parking Lot
total cost of Phase 1 projects
The total cost of all Phase 1 projects is estimated at $3,681,164. This cost includes construction contingency, construction management fees, and design costs. This leaves the district with an estimated $818,836 remaining to address Phase 2 projects.
timeline of phase 1 projects
Phase 1 projects are scheduled to begin May 22, and conclude by the time school starts again on September 1st.
General Contractor
We're proud to partner with Kraemer Bros. Construction as the school district's General Contractor, managing the selection of subcontractors, timelines, and project completion. The district previously worked with Kraemer Bros. in the construction of the new school in 1990-91, and the building addition in 1996. We proudly support a successful business based out of southwest Wisconsin (Plain, WI).
local subcontractors
We are happy to support and partner with several western and southwestern Wisconsin subcontractors to complete work on our Phase 1 projects. Local subcontractors that will be on site completing work this summer include Hall Ceilings out of Eastman; La Crosse Glass out of La Crosse; Showen Excavating out of Gays Mills; Winona Heating and Ventilation out of La Crosse; McCormick Electric out of Gays Mills; and Kraemer Bros. Construction out of Plain.