District Construction Update

Week of August 7th

District ConstructionUpdateWeek of August 7th

Week 12 - Projects Beginning to Wrap Up

Many construction projects in the district are at or nearing completion. We anticipate all major construction wrapping up in the next two weeks, with the possibility of some minor details and finishes to complete after that.
Construction Mobilization

ONGOING PROJECTS ONGOING PROJECTS

ROOF REPLACEMENT

The roofing contractors have completed installing the new rubber roof. There are still finishing details that need to be completed, making the roof over 90% complete.
zoom_out_map

NEW EPDM ROOF OVER MIDDLE SCHOOL WING

UPPER WALL EIFC

Contractors from MUZA Sheet Metal will be back on site this week finishing up installation of the new horizontal sheet metal on the upper EIFC. The new siding will provide a more efficient system to keep water from leaking into the building, as well as provide an updated and modern look to the building.
zoom_out_map

METAL WALL PANELING ON UPPER EIFC

zoom_out_map

PORTION OF COMPLETED WALL

zoom_out_map

FRONT VIEW SHOWING STAGES OF EIFC INSTALL

NEW EXTERIOR WINDOWS

Installers from La Crosse Glass continued installation of the new windows this week. All ground floor and second level windows will be replaced in the building. There are a few windows in the office and library areas that need to be replaced, otherwise all other windows in the building have been installed. There is still finishing work on the exterior and interior of the windows that needs to be completed. The new ground floor windows will be a two panel aluminum window with horizontal slide. The new upper windows are fixed windows. The new windows will be much more energy-efficient, as well as giving the building a more modern look. Not to mention the amount of natural light the windows will give the classrooms and office spaces.
zoom_out_map

VIEW OF FINISHED WINDOW INSTALLATION

New solid surface sill on inside along with aluminum wrapped trim.
zoom_out_map

NEW UPPER LEVEL WINDOWS

zoom_out_map

OUTSIDE VIEW OF WINDOW INSTALLATION PREP

LOCKER ROOM RENOVATIONS

Contractors from Protective Coatings Specialists out of Appleton, WI were on site this week to begin installing the new epoxy floors. Several of the showers and bathrooms were completed this past week. This week, the plumbers will return to the district to finish installing fixtures and hardware, as well as electricians and HVAC completing their installations.
zoom_out_map

BOYS MIDDLE SCHOOL LOCKER ROOM

zoom_out_map

GIRLS MIDDLE SCHOOL LOCKER ROOM

BATHROOM ADDITIONS

New epoxy flooring has been poured in most of the new and existing bathrooms. Plumbers will be back onsite this week to begin installing fixtures and putting the finishing touches on the bathrooms.
zoom_out_map

HIGHLIGHTED AREAS OF NEW BATHROOMS

zoom_out_map

SINGLE REST ROOM BEHIND LARGE GYM

zoom_out_map

TRIPLE RESTROOMS NEAR PERFORMANCE CENTER

ELEMENTARY CABINETS

The NC Maintenance crew has installed all new elementary cabinets. The cabinet makers, Foggy Bottoms, have installed all the new countertops, and made sure all the doors are hung and spaced correctly to give a final finished look. Strange Plumbing will be onsite to install the new classroom sinks and fixtures. We're excited for the additional storage space the new cabinets will provide, as well as providing a fresh new look in the elementary classrooms.
zoom_out_map

ELEMENTARY CLASSROOM CABINETS

zoom_out_map

ELEMENTARY CLASSROOM CABINETS

zoom_out_map

ELEMENTARY CLASSROOM CABINETS

NEW FLOORING

A crew from Protective Coating Specialists was onsite this past week to begin pouring the new epoxy flooring. The epoxy floors will replace old tile floors in the Commons and Bathrooms, hallway behind the Large Gym, maintenance hallway, Art hallway, and back middle school hallway, cafeteria, area outside of the Performance Center, and the existing flooring in the front hallway. Areas completed this past week included the Commons and bathrooms, hallway behind large gym, cafeteria, and area outside of the Performance Center. The crew will be onsite the next two weeks finishing the other areas.
zoom_out_map

FINISHED EPOXY FLOORING - COMMONS

zoom_out_map

FINISHED EPOXY FLOORING - HALLWAY

zoom_out_map

FINISHED EPOXY FLOORING - CAFETERIA

LIBRARY RENOVATIONS

The Library renovation project has seen the completion of new paint in the entire space, as well as new carpet tiles being installed in the entire space. We installed new Luxury Vinyl Tile in one small space which is used as a Makerspace in the Library for students. Later this summer we will see the installation of a new circulation desk, and new shelving and furnishing will be added throughout the school year. This is an ongoing project that likely won't be fully completed until later in the school year.
zoom_out_map

LIBRARY CARPET AND CABINETRY

zoom_out_map

LIBRARY CARPETING - MS/HS SIDE

zoom_out_map

LIBRARY CARPETING - ELEMENTARY SIDE

DAYCARE RENOVATIONS

We are excited to be able to expand our district daycare this year and add two additional classrooms. This will give us a total of four daycare rooms, allowing us to better divide the age levels, as well as increase the number of children and families we can provide care for. The daycare renovation project includes renovating the bathroom space to create a second bathroom, carpeting the two new infant and baby rooms, and installing a hallway door divider for continued noise reduction and privacy.
zoom_out_map

BATHROOM RENOVATIONS IN DAYCARE WING

zoom_out_map

NEW HALLWAY DIVIDER FOR DAYCARE WING

zoom_out_map

NEW CARPET IN 0-1 YEAR OLDS ROOM

COURTYARD DRAINAGE PROJECT

The sidwalks in the courtyard have been torn out, and regrading began in the courtyard area. An additional manhole has been installed in the courtyard, the entire area will be regraded, and a new concrete sidewalk has been poured. This project will allow water to drain properly, preventing any leakage into the building from water runoff.
zoom_out_map

EXCAVATION OF COURTYARD

zoom_out_map

NEW CONCRETE POURED IN COURTYARD

zoom_out_map

INSTALLATION OF NEW MANHOLE IN COURTYARD

SMALL GYM FLOOR REPLACEMENT

A small section of the Small Gym that received water damage last summer has been removed. In the coming weeks, new flooring will be installed in that area. The entire floor will be sanded, repainted, and refinished, resulting in a new Small Gym floor.
zoom_out_map

SECTION OF SMALL GYM FLOOR REMOVED

zoom_out_map

SMALL GYM FLOOR BEFORE

NEW GREENHOUSE

This past week the district broke ground on the site of the new North Crawford Greenhouse. The new 24' x 48', state of the art greenhouse, will serve the North Crawford Ag and FFA programs, as well as other classrooms and programs at North Crawford. We hope to partner with the community in the future to best utliize our greenhouse space. The greenhouse will be constructed later this fall.

COMPLETED PROJECTS COMPLETED PROJECTS

PARKING LOT AND SIDEWALK REPLACEMENT

New concrete parking lots and sidewalks have been poured. Fill is being added along all sidewalks and parking lots, with new grass seed being planted. All parking lots are open for visitor parking. Visitors to the building should park in the front or side parking lot. The back parking lot continues to be used by construction vehicles. The concrete parking lots will save the district thousands in maintenance each year over asphalt parking lots and sidewalks.
zoom_out_map

FRONT (SOUTH) PARKING LOT

zoom_out_map

STUDENT (WEST) PARKING LOT

zoom_out_map

VIEW OF FRONT (SOUTH) PARKING LOT

LARGE GYM FLOOR

Resurfacing of the large gym floor has been completed. We were happy to welcome our athletic teams back into the gym this past week for open gym. Stalker Sports Floors did a remarkable job of giving us a beautiful gym floor that we can be proud of for years to come.

UPCOMING PROJECTS UPCOMING PROJECTS

Several projects will be kicking off over the next couple of weeks. Those projects include:


  • Refinishing Small Gym Floor
  • Installation of Concrete Pad for New Greenhouse
  • Renovation of Upper Maintenance Shed
  • Installation of New Circulation Desk in the Library
zoom_out_map

ACCESS TO BUILDING

Much of our building is still accessible to staff, students, and the public. All of our parking lots are once again opened for visitor parking. We ask all visitors to the building to park in the front or side parking lot. The back parking lot is reserved for construction vehicles. This week, the maintenance hallway, Art hallway, and back middle school hallway, bathrooms, and locker rooms are off limits due to new flooring installation. All other areas of the building continue to be accessible.
zoom_out_map

GENERAL CONTRACTOR

We're proud to partner with Kraemer Bros. Construction as the school district's General Contractor, managing the selection of subcontractors, timelines, and project completion. The district previously worked with Kraemer Bros. in the construction of the new school in 1990-91, and the building addition in 1996. We proudly support a successful business based out of southwest Wisconsin (Plain, WI).
zoom_out_map

ENGINEERING, ARCHITECTURE, AND DESIGN

The district has been working with FEH Design out of Dubuque, IA for the past year on the design, architecture, and engineering of our projects. Kevin and his team at FEH assisted the district through the pre-referendum process, facilitating several community meetings and a community survey. They stayed with us through the referendum, and continue to work with the district on any design or architectural changes as construction is happening.
zoom_out_map

BOOTS ON THE GROUND

We are happy to support and partner with several Wisconsin subcontractors to complete work on our projects. Several of these subcontractors are from right here in southwest and western Wisconsin. Contractors and subcontractors on site this past week included:

Kraemer Bros. - Plain, WI

Higher Ground Roofing - Kewaskum, WI

MUZA Sheet Metal Company - Oshkosh, WI

Zimmerman Plumbing - Portage, WI

McCormick Electric - Gays Mills, WI

Winona Heating and Ventilation - La Crosse, WI

Showen Excavating - Gays Mills, WI

La Crosse Glass - La Crosse, WI

Luther & Weber Painting - Spring Green, WI

Hall Ceilings - Steuben, WI

Momchilovich Drywall & Paint - Platteville, WI

LARGE SCHOOL OPPORTUNITIES, SMALL SCHOOL VALUES LARGE SCHOOL OPPORTUNITIES, SMALL SCHOOL VALUES

zoom_out_map

North Crawford School District

Email: bmunson@ncrawford.k12.wi.us
Website: www.northcrawford.com
Location: 47050 County Road X, Soldiers Grove, WI, USA
Phone: (608) 735-4318
Facebook: https://www.facebook.com/profile.php?id=100057263208876
Twitter: @northcrawford

Loading indicator

close

Created with Smore

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter
Get started with free school newsletter templates!